Potential penalties for contractors on Corridor 10 due to late works – Aktor and Azvi required to fix problems
Comments
(Photo: Blazej Lyjak/shutterstock.com)
The newspaper reports that the Greek Aktor has been requested to fix the problems on the section from Prosek to Crvena Reka, whereas Azvi has been given another warning, due to the section from Grdelica to Caricina Dolina. If the mistakes are not fixed in a reasonable amount of time, the companies stand to be penalized.
Due to the works being late on Corridor 10, the investors, the Roads of Serbia and the Corridors of Serbia, have so far terminated the contracts with two unconscientious contractors – the Austrian Alpine and the Bulgarian Trace, Novosti reminds.
The Roads of Serbia have issued penalties worth around RSD 901 billion on their construction sites in the past 12 years. Last year, the Highway Institute, Srbija Autoput, Planum and Osijek-based Werkos were the subject of penalties.
Companies:
Koridori Srbije d.o.o. Beograd
AKTOR A.T.E. Ogranak Beograd
AZVI Novi Sad
Rubau Ogranak Beograd
Alpine d.o.o. Beograd
Institut za puteve a.d. Beograd
TRACE GROUP HOLD PLC OGRANAK BEOGRAD
GP Planum Zemun
Srbijaautoput d.o.o. Beograd
WERKOS d.o.o. - OSIJEK
Tags:
Koridor 10
deonica Prosek Crvena reka
deonica Grdelica Caričina Dolina
Alpina
Trace Bugarska
Srbija autoput
Werkos iz Osijeka
gradnja autoputeva
putevi u Srbiji
Comments
Your comment
Most Important News
Full information is available only to commercial users-subscribers and it is necessary to log in.
Follow the news, tenders, grants, legal regulations and reports on our portal.
Registracija na eKapiji vam omogućava pristup potpunim informacijama i dnevnom biltenu
Naš dnevni ekonomski bilten će stizati na vašu mejl adresu krajem svakog radnog dana. Bilteni su personalizovani prema interesovanjima svakog korisnika zasebno,
uz konsultacije sa našim ekspertima.